Nuclear-power stocks slumped on Monday after US regulators barred a plant from supplying extra power to an Amazon data center ...
Big tech companies need lots of electricity for their data centers, which are processing increasingly complex artificial ...
Amazon’s plans have also hit a snag. The company is planning to build a new hyperscale data center next to the nuclear power ...
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to tap into ...
The denial of a power agreement tied to Amazon Web Services' nuclear data center campus could slow a potential wave of ...
The proposal would have boosted the amount of electricity coming from the Pennsylvania power plant from 300 megawatts to 480 ...
Nuclear-energy stocks slid after the Federal Energy Regulatory Commission shot down Amazon's plan to use more power from a Talen Energy nuclear reactor to fuel a data center. The decision is a si ...
Democratic Chair Willie Phillips dissented, arguing that the order was a roadblock to "a new phase in the energy transition." ...
The commission agreed with opponents of the proposal, citing concerns about grid reliability and cost fairness.
The Amazon data center is located close to Talen's Susquehanna nuclear power plant in Pennsylvania, as previously reported. The amended interconnection deal would have supplied more power directly ...
The Federal Energy Regulatory Commission has rejected a request to increase the energy sent to Amazon's data centers from a ...
Shares of Talen Energy (TLN) are under pressure on Monday after the Federal Energy Regulatory Commission, or FERC, rejected an amended ...