Nuclear-power stocks fell after regulators voted against a deal between Amazon and Talen Energy. The deal would permit a ...
The Federal Energy Regulatory Commission (FERC) rejected an effort Friday to allow an Amazon data center to tap into ...
The proposal would have boosted the amount of electricity coming from the Pennsylvania power plant from 300 megawatts to 480 ...
Amazon.com Inc. said it’s committed to building a data center campus adjacent to a Pennsylvania nuclear plant after the top ...
Amazon’s plans have also hit a snag. The company is planning to build a new hyperscale data center next to the nuclear power ...
Constellation Energy ( NASDAQ: CEG) -10.1%, the biggest loser on the S&P 500, in early trading Monday after the Federal ...
Big tech companies need lots of electricity for their data centers, which are processing increasingly complex artificial ...
Talen said it believed FERC had erred and was evaluating its options. The company can still restructure its expanded deal ...
The Amazon data center is located close to Talen's Susquehanna nuclear power plant in Pennsylvania, as previously reported. The amended interconnection deal would have supplied more power directly ...
The Federal Energy Regulatory Commission (FERC) denied an amended Interconnection Service Agreement (ISA) that would have ...
The Federal Energy Regulatory Commission has rejected a request to increase the energy sent to Amazon's data centers from a ...
Axios reported today that Amazon’s project recently failed to secure a key regulatory approval. Meta’s planned data center campus, in turn, is said to have raised environmental concerns.