The project will construct a new open space at the DEP site on East 4th Street between Bowery and Lafayette Street. The completion date has changed. To learn more about why schedules change, please ...
This project will reconstruct the existing skate park with new skate elements, fencing, benches, picnic tables, and landscaping at West 109th Street in Riverside Park. The completion date has changed.
This project will remove invasive species and plant new and replacement trees at Ridgewood Reservoir in Highland Park. Due to COVID related impacts, this project may have experienced schedule delays.
This project will construct bollards and other security measures at entrances to Coney Island Boardwalk. The completion date has changed. To learn more about why schedules change, please visit the How ...
10:00 a.m.–3:00 p.m. Art From the Heart, arranged by the Tottenville Historical Society at the historic H.H. Biddle House features vintage paintings from their collection.
This project will reconstruct and expand the playground in Kelly Park, including play equipment, spray shower, swings, seating areas, benches, security lighting, fencing, drainage and water supply, ...
Project Update: A meeting was held with stakeholders to discuss the scope of work for the project. Parks is now reviewing feedback from the meeting and the scope of work to determine the schedule for ...
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page. The average time for procurement is 9-12 months. The procurement timeline for this ...
Project Update: The schematic design for this project has been approved internally at Parks and is now going through review by the community board and external regulatory agencies for comment and ...
Project Update: Parks staff members are reviewing construction documents for this project. The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be ...
This project will reconstruct the staircase and pathways, including pavement, drainage, lighting and planting, in Highbridge Park. The completion date has changed. To learn more about why schedules ...
Unanticipated conditions were discovered and this project is being reevaluated. Due to COVID related impacts, this project may have experienced schedule delays. The completion date has changed. To ...